• Connect With Us
Expansion Project Timeline 

  • Overall duration of expansion project – approximately 36 months


  • Building demo: Q3 2019


  • Site excavation: Q1 2020


  • Garage complete: Q2 2021


  • Pavilion complete: Q4 2022


Key Project Contacts
Patients & Visitors

Pardon the Site Work as We Prepare for the New Outpatient Pavilion


In November 2018, the Arlington County Board  approved plans for the first major expansion of Virginia Hospital Center since 2004. The center- piece of this project is the creation of a new Outpatient Pavilion, which will provide direct, easy access for patients from their arrival at the parking garage to treatment areas. Underground utility work is required to support the new Outpatient Pavilion and Parking Structure.


Utility Work Timeline On Campus:

  • Begin mid June 2019
  • Finish end of September 2019
Download Logistics Maps 


What is Being Done to Ensure a Safe Campus:

  • Traffic will become one way IN ONLY from George Mason at various points in the project
  • Traffic into the Green Garage will be IN ONLY at certain times, and will exit out the back onto Edison St.
  • Signage and Traffic Personnel will always be present
  • All VHC staff enter campus from Edison St. only

Project Update: Next 4 weeks (posted 11/05/19)

  • Continuation of site clearing
  • Continuation of building demolition
  • Shoring contractor mobilization and start of soldier pile
  • Excavation contractor mobilization
  • Stormwater and sanitary utilities work
  • Ductbank work at 19th St & N. George Mason
  • Construction trailer assembly

Timelapse Video: Updated Novmeber 4, 2019



Week of July 21, 2019


It’s official!
Virginia Hospital Center and Arlington County agreed to the Hospital’s acquisition of the Edison property and the transfer of the Carlin Springs property to the County. Thanks to the VHC Board of Directors and the many supporters of the expansion and our plans to better serve our community.


Week of July 1, 2019

 

The underground utility construction began last week and will continue for the next several weeks. This week begins roadway work.  

The following activities will take place the week of July 1:

  1. Excavation in the parking lot in front of Medical Office Building C (1715 bldg).
  2. Excavation in front of Medical Office Building C (1715 bldg). Flagmen will be present.
  3. Excavation in front of the Outpatient Clinic.  The roadway will be one-way traffic at times.  Flagmen and detour signage will be present.
  4. For greater safety and traffic control, we will set new manholes in place on July 6.

Project Update – Next 4 weeks (posted 11/05/19)

·         Continuation of site clearing

·         Continuation of building demolition

·         Shoring contractor mobilization and start of soldier piles

·         Excavation contractor mobilization

·         Stormwater and sanitary utilities work

·         Ductbank work at 19th St & N. George Mason

·         Construction trailer assembly

Share:
Community Engagement Meetings
How Can I Learn More?


View plans and updates by 
downloading the Project Corners App

Download the App 

1701 N. George Mason Drive | Arlington, VA 22205-3698 | tel 703.558.5000
© 2019 Virginia Hospital Center All rights reserved