Expansion Project Timeline 

  • Overall duration of expansion project – approximately 36 months


  • Building demo: Q3 2019


  • Site excavation: Q1 2020


  • Garage complete: Q2 2021


  • Pavilion complete: Q4 2022


Key Project Contacts
Patients & Visitors

Pardon the Site Work as We Prepare for the New Outpatient Pavilion


In November 2018, the Arlington County Board  approved plans for the first major expansion of Virginia Hospital Center since 2004. The center- piece of this project is the creation of a new Outpatient Pavilion, which will provide direct, easy access for patients from their arrival at the parking garage to treatment areas. Underground utility work is required to support the new Outpatient Pavilion and Parking Structure.


Utility Work Timeline On Campus:

  • Begin mid June 2019
  • Finish end of September 2019
Download Logistics Maps 


What is Being Done to Ensure a Safe Campus:

  • Traffic will become one way IN ONLY from George Mason at various points in the project
  • Traffic into the Green Garage will be IN ONLY at certain times, and will exit out the back onto Edison St.
  • Signage and Traffic Personnel will always be present
  • All VHC staff enter campus from Edison St. only
Share:
Community Engagement Meetings


Monday, June 17, 2019
 
Tara-Leeway Heights Community meeting

Wednesday, June 26, 2019 
Langston Brown/Halls Hill Community meeting, Langston Brown Community Center at 7:30pm

Tuesday, July 16, 2019
Open Community Forum, VHC Auditorium at 7:00pm

Thursday, July 18, 2019
Open Community Forum, VHC Auditorium at 7:00pm

View the Presentation


How Can I Learn More?


View plans and updates by 
downloading the Project Corners App

Download the App 